All The Open Group exams

Free OGEA-101 practice test: 30 questions with answers

30 original questions for TOGAF Enterprise Architecture Part 1 (Foundation), drawn from every topic area. Answer each one to see whether you got it right and why. No sign-up.

Free questions
30
Full bank
112 questions
Real exam
40 questions, 60 min
Passing score
60% (24 of 40)

OGEA-101 exam guide: topics, cost and format

All 30 OGEA-101 questions with answers

The same questions as the test above, grouped by exam topic. Open any question to see the answer and explanation.

Concepts of Enterprise Architecture and the TOGAF Standard (5 questions)

  1. Question 1

    A newly appointed head of architecture at a retail group wants one repeatable method that every business unit's architects follow, so their outputs can be compared. Which TOGAF component should she adopt as the core process?

    1. AA catalog of Solution Building Blocks for each product line
    2. BThe Architecture Development Method (ADM)
    3. CA taxonomy of reusable assets in the Architecture Continuum
    4. DA stakeholder map showing power and interest for each business unit
    Show answer and explanation
    Correct answer: B

    The Architecture Development Method is the repeatable process TOGAF provides for developing architectures, so it meets the need for one shared method. Solution Building Blocks are implementation components, the Architecture Continuum classifies reusable assets, and a stakeholder map is an engagement technique rather than a process for building architecture.

  2. Question 2

    In the TOGAF Standard, how is an enterprise defined?

    1. AAny collection of organizations that has a common set of goals
    2. BA government department that funds large technology programs
    3. CA software platform shared by several business units across regions
    4. DA single legal entity that owns and operates its own IT systems
    Show answer and explanation
    Correct answer: A

    TOGAF defines an enterprise as any collection of organizations sharing a common set of goals, which can be a company, a government, or a partnership. The other options narrow the term to a legal entity, a government department or a software platform, none of which matches the TOGAF definition.

  3. Question 3

    A consultant briefs a board on enterprise architecture and the TOGAF Standard. Which two statements are accurate? (Choose two.)

    1. AThe TOGAF Standard is a framework and method for developing enterprise architecture
    2. BThe TOGAF Standard requires one specific vendor's product in every architecture repository
    3. CEnterprise architecture helps align business goals with the information technology that supports them
    4. DEnterprise architecture replaces the need for an organization to set its own business strategy
    Show answer and explanation
    Correct answer: A, C

    TOGAF is an open, vendor-neutral framework and method for enterprise architecture, and enterprise architecture is used to align business goals with the supporting IT. The other two statements are wrong because TOGAF does not mandate a vendor product and enterprise architecture informs strategy rather than replacing it.

  4. Question 4

    A project sponsor wants to fund only technology upgrades and questions why the architecture team is also reviewing business processes and data. Which explanation is most consistent with the TOGAF Standard?

    1. ABusiness processes are reviewed only after technology is fixed, in the final phase of the cycle
    2. BData is out of scope for this engagement, so the team reviews only the applications and technology platforms in use
    3. CArchitecture work is limited to the IT department, so business processes belong to another team
    4. DArchitecture covers business, data, application and technology, so a change in one domain affects the others
    Show answer and explanation
    Correct answer: D

    TOGAF treats enterprise architecture as spanning business, data, application and technology architectures, which are developed together because they depend on each other. The other options wrongly delay business review, restrict scope to IT, or drop data entirely.

  5. Question 5

    A regional government agency wants to adopt the TOGAF Standard, but its existing governance committees and approval steps differ from those described in the framework. What is the most appropriate approach?

    1. AAdopt the framework exactly as published and reorganize the agency's committees so they match the TOGAF roles and steps
    2. BAdapt the framework, tailoring its roles and processes to the agency's governance while keeping the core method
    3. CReject the framework, since it cannot be used by any organization whose governance differs from the standard model
    4. DUse only the glossary of terms, since the method can be applied only by organizations that match its structure
    Show answer and explanation
    Correct answer: B

    TOGAF is designed to be adapted to an organization's own governance and needs, so the agency tailors roles and processes while keeping the core method. Adopting it unchanged, rejecting it, or using only the glossary all ignore that design.

Key terminology of the TOGAF Standard (5 questions)

  1. Question 6

    Which description matches the TOGAF term 'deliverable'?

    1. AA work product such as a diagram, catalog or matrix produced during architecture work
    2. BA reusable component that delivers a defined functionality within a solution
    3. CA formal output that is agreed with stakeholders and is contractually defined
    4. DA group of people or organizations that has an interest in the architecture
    Show answer and explanation
    Correct answer: C

    In TOGAF, a deliverable is a formal, contractually agreed output of an architecture project that is reviewed and signed off. The first option describes an artifact, the second a building block, and the third a stakeholder, so none of them is the deliverable.

  2. Question 7

    The TOGAF Standard groups architecture work products into three categories. Which set is correct?

    1. ACatalogs, matrices and diagrams
    2. BBaseline, target and transition architecture states
    3. CCatalogs, principles and implementation roadmaps
    4. DStakeholder views, viewpoints and concerns
    Show answer and explanation
    Correct answer: A

    The Architecture Content Framework describes architecture work products as artifacts, and artifacts are grouped as catalogs, matrices and diagrams. Principles and roadmaps, baseline and target states, and views with concerns are other kinds of content rather than these three categories.

  3. Question 8

    What does the TOGAF term 'baseline architecture' refer to?

    1. AA reusable template that specifies how a solution building block is implemented
    2. BThe intermediate architecture that exists while the migration from current to target is in progress
    3. CThe desired architecture at a future point in time that the enterprise aims to reach
    4. DA description of the current architecture at a specific point in time, used as a starting point
    Show answer and explanation
    Correct answer: D

    A baseline architecture is the as-is description of the architecture at a given point in time, and it is compared with the target architecture during gap analysis. The desired future state is the target architecture, the intermediate state is a transition architecture, and a template is a pattern or template rather than a baseline.

  4. Question 9

    During a stakeholder workshop, an architect explains TOGAF terms to new team members. Which two definitions are correct? (Choose two.)

    1. AA viewpoint is a representation of the whole system from the perspective of related concerns
    2. BA concern is a key interest that is crucially important to one or more stakeholders in a system
    3. CA view is a specification of the conventions for one kind of model used to create views
    4. DA building block is a potentially re-usable component of business, IT or architectural capability
    Show answer and explanation
    Correct answer: B, D

    A concern is a key interest of stakeholders, and a building block is a potentially reusable component of business, IT or architectural capability. The other two options swap the definitions of view and viewpoint, a common source of confusion.

  5. Question 10

    Which part of the Architecture Repository holds the standards, policies and rules that the enterprise must apply to its architecture work?

    1. AThe Reference Library, which holds reference models and patterns for reuse
    2. BThe Architecture Landscape, which shows the assets in use or planned at each level
    3. CThe Governance Log, which records decisions made during architecture governance
    4. DThe Standards Information Base, which holds the standards that must be applied
    Show answer and explanation
    Correct answer: D

    The Standards Information Base holds the standards, policies and rules that the enterprise must apply to its architecture work. The Reference Library holds reference models and patterns, the Governance Log records decisions, and the Architecture Landscape shows the assets in use or planned.

Architecture Development Method (ADM) cycle (4 questions)

  1. Question 11

    Which ADM phase establishes the architecture capability, such as principles, framework tailoring and governance arrangements, before any specific architecture project begins?

    1. APhase A, which validates the business context, defines the scope and produces the Architecture Vision and statement of work
    2. BThe Preliminary Phase, which establishes the architecture capability, principles and framework
    3. CPhase G, which governs implementation against the target architecture
    4. DPhase H, which manages changes to the architecture after deployment
    Show answer and explanation
    Correct answer: B

    The Preliminary Phase prepares the organization by establishing the architecture capability, including frameworks, principles and governance arrangements. Phase A starts a specific architecture project, Phase G governs implementation, and Phase H handles change, so none of those prepares the capability.

  2. Question 12

    A sponsor asks which ADM phase will validate the business context for a new project, define its scope, and produce a vision that the sponsor approves before detailed architecture work begins. Which phase should the architect name?

    1. APhase B, Business Architecture, which models the baseline and target business
    2. BPhase E, Opportunities and Solutions, which identifies delivery vehicles
    3. CPhase F, Migration Planning, which sequences the implementation projects
    4. DPhase A, Architecture Vision, which produces the approved vision and scope
    Show answer and explanation
    Correct answer: D

    Phase A validates the business context, defines the scope and produces the Architecture Vision, which the sponsor approves before detailed work starts. Phase B develops the business architecture, while Phases E and F come later and deal with delivery options and migration sequencing.

  3. Question 13

    A program office already has the target architecture and gap analysis. It now needs to finalize the sequence of implementation projects and produce an implementation and migration plan based on cost-benefit and risk assessments. Which ADM phase covers this work?

    1. APhase E, Opportunities and Solutions, which identifies the major implementation approaches and delivery projects
    2. BPhase G, Implementation Governance, which oversees projects once they start
    3. CPhase F, Migration Planning, which finalizes the implementation and migration plan
    4. DPhase H, Architecture Change Management, which handles later changes
    Show answer and explanation
    Correct answer: C

    Phase F is where the implementation and migration plan is finalized, with projects prioritized using cost-benefit and risk assessment. Phase E identifies implementation options before this, Phase G governs the implementation once it starts, and Phase H manages later architecture changes.

  4. Question 14

    Which two statements about adapting and scoping the ADM are correct? (Choose two.)

    1. AEvery ADM step and deliverable must be completed in full for every architecture project
    2. BThe ADM should be tailored to the scope, timeframe and needs of each architecture engagement
    3. CScope is fixed in the Preliminary Phase and cannot be revisited in later iterations
    4. DSteps that add no value to a specific engagement may be omitted, provided the change is justified
    Show answer and explanation
    Correct answer: B, D

    The ADM is meant to be tailored to the scope, timeframe and needs of each engagement, and steps can be adjusted or omitted when there is a justification. Requiring every step in full ignores that flexibility, and scope can be revisited in later iterations rather than being fixed for good.

Techniques supporting the ADM (4 questions)

  1. Question 15

    Which technique compares the baseline architecture with the target architecture to identify what is missing, mismatched or needs to change?

    1. ABusiness scenarios, which capture actors, goals and processes to derive requirements
    2. BArchitecture patterns, which record reusable solutions to recurring problems
    3. CGap analysis, comparing baseline and target architectures
    4. DStakeholder management, which identifies and engages people who have concerns
    Show answer and explanation
    Correct answer: C

    Gap analysis is a TOGAF technique that compares the baseline architecture with the target architecture to identify gaps. The other techniques support requirements capture, reusable solutions and stakeholder engagement rather than comparing architecture states.

  2. Question 16

    An architecture team keeps solving the same integration problem on different projects. It wants a standard, reusable description of a proven solution to a recurring problem. Which technique should it use?

    1. AArchitecture patterns, which document reusable solutions to recurring problems
    2. BMigration planning techniques, which sequence the implementation of projects over time
    3. CCapability-based planning, which links business capabilities to planned investment
    4. DRisk management, which identifies and treats risks to the architecture program
    Show answer and explanation
    Correct answer: A

    Architecture patterns describe reusable solutions to recurring problems, which fits a team that solves the same integration problem repeatedly. The other techniques deal with migration sequencing, investment planning and risk, and none of them provides a reusable solution description.

  3. Question 17

    A business analyst must validate requirements by describing how specific actors use a business process to reach their goals, step by step. Which TOGAF technique supports this?

    1. AInteroperability requirements, which set standards for data exchange between systems
    2. BBusiness transformation readiness assessment, which scores organizational readiness
    3. CBusiness scenarios, which describe actors, goals and processes in a narrative form
    4. DArchitecture principles, which set general rules that guide design decisions
    Show answer and explanation
    Correct answer: C

    Business scenarios are a TOGAF technique that describe the actors, roles, goals and processes involved, which helps validate and derive requirements. Interoperability requirements, readiness assessments and principles address other needs and do not describe how actors achieve their goals.

  4. Question 18

    Which two statements about architecture principles in the TOGAF Standard are correct? (Choose two.)

    1. AA principle names the specific vendor product that must be used across the enterprise
    2. BEach principle is recorded with a name, a statement, a rationale and its implications
    3. CPrinciples are fixed once approved and can never be revised during later ADM cycles
    4. DPrinciples should be understandable and stable, with a rationale that ties to business benefit
    Show answer and explanation
    Correct answer: B, D

    TOGAF records each principle with a name, statement, rationale and implications, and principles should be understandable and stable with a rationale tied to business benefit. Naming a vendor product is wrong because principles set general rules, and principles can be revised through governance rather than being frozen.

Applying the ADM (4 questions)

  1. Question 19

    A bank's architecture team has finished its information systems work for a retail division. New regulation then arrives, so the team loops back to revisit its business architecture before continuing. What is this return to an earlier stage called in the ADM?

    1. APartitioning of the architecture into smaller, independent segments
    2. BA formal compliance review carried out by the Architecture Board
    3. CAn iteration of part of the ADM cycle, revisiting an earlier phase
    4. DArchitecture change management under Phase H of the cycle
    Show answer and explanation
    Correct answer: C

    Iteration means revisiting earlier parts of the ADM when new requirements or conditions arise, so looping back to Phase B is an iteration. Partitioning divides the architecture work, Phase H covers changes after deployment, and a compliance review is a governance activity, so none of the other options describes revisiting an earlier phase.

  2. Question 20

    A global insurer splits its architecture work into separate segments for each regional business so teams can work in parallel within agreed boundaries. What is this approach called in the TOGAF Standard?

    1. AArchitecture partitioning, dividing architecture work into segments with agreed boundaries
    2. BConsolidation of every regional business into one single enterprise architecture
    3. CStopping the ADM after Phase A until the sponsor has approved the scope
    4. DIteration, repeating the same phase again and again until the full scope of the work is exhausted in one pass
    Show answer and explanation
    Correct answer: A

    Architecture partitioning divides the architecture into smaller segments with clear boundaries so that teams can work in parallel. Iteration repeats parts of the cycle rather than splitting the work, consolidation runs against partitioning, and stopping after Phase A is not a way of dividing work.

  3. Question 21

    A retailer is extending its architecture work to customer-facing digital channels. The architects want to keep the ADM but focus on what matters most for digital customers. Which approach is most consistent with the TOGAF Standard?

    1. AReplace the ADM with a separate digital method, since the ADM only applies to back-office systems
    2. BKeep using the ADM, tailoring scope and cadence to the digital initiative while still covering business, data, application and technology
    3. CLimit the work to the technology domain, because digital channels are mainly a matter of infrastructure
    4. DExempt digital initiatives from architecture governance so that they can launch faster than other work
    Show answer and explanation
    Correct answer: B

    The ADM can be applied to digital enterprise work by tailoring its scope and cadence while still considering business, data, application and technology architectures. The other options wrongly say the ADM is only for back-office systems, that digital work needs only infrastructure, or that governance can be dropped.

  4. Question 22

    A product team delivers in two-week sprints and needs architecture guidance without slowing delivery. Which approach from the TOGAF Standard best supports this?

    1. AComplete every ADM phase in full before the first sprint starts, then lock the architecture for the project
    2. BRun the ADM in short, iterative cycles, producing just enough architecture for each sprint and refining it as delivery proceeds
    3. CDefer all architecture governance to Phase H, after the product has been released to customers
    4. DSkip architecture work altogether, because agile teams organize their own design decisions
    Show answer and explanation
    Correct answer: B

    Running the ADM in short iterations, with just enough architecture for each sprint, fits agile delivery and keeps architecture aligned with the team's pace. Completing all phases up front, dropping architecture entirely, or deferring governance to Phase H would either delay delivery or leave the work ungoverned.

Architecture Governance (4 questions)

  1. Question 23

    Which governance body oversees the architecture, checks compliance and resolves architecture issues across projects in the TOGAF Standard?

    1. AThe program management office, which tracks project budgets and schedules
    2. BThe enterprise architecture team, which produces the architecture deliverables
    3. CThe architecture repository, which stores architecture assets and models
    4. DThe Architecture Board, which oversees architecture and resolves issues across projects
    Show answer and explanation
    Correct answer: D

    The Architecture Board is the TOGAF governance body that oversees architecture, checks compliance and resolves issues across projects. The program office tracks budgets, the architecture team produces deliverables, and the repository stores assets, so none of them is the governance body.

  2. Question 24

    A project team and its sponsor must agree the deliverables, quality expectations and service levels for an architecture implementation. Which governance instrument records this joint agreement?

    1. AThe gap analysis, which compares baseline and target architectures
    2. BThe Architecture Vision, which summarizes the target business value and the scope that the sponsor has approved
    3. CThe Architecture Principles, which set general rules for design decisions
    4. DThe Architecture Contract, which records the joint agreement between sponsors and development partners
    Show answer and explanation
    Correct answer: D

    An Architecture Contract is a joint agreement between sponsors and development partners on deliverables, quality and fitness for purpose. The Architecture Vision, the principles and the gap analysis are important architecture outputs or techniques, but none of them records the agreement between the parties.

  3. Question 25

    An architect checks a delivered solution against the target architecture and the agreed principles, using a checklist, and records the outcome. What is this activity?

    1. AAn architecture compliance review, checking conformance with the target architecture
    2. BGap analysis between baseline and target states, which lists the differences that must be closed during planning
    3. CA business scenario workshop with stakeholders that captures their goals, actors and business processes
    4. DA stakeholder map of power and interest, used to decide how much engagement each stakeholder needs
    Show answer and explanation
    Correct answer: A

    A compliance review checks whether a solution conforms to the target architecture and the principles, and TOGAF governance relies on such reviews. Gap analysis compares states during planning rather than checking a delivered solution, while a business scenario workshop and a stakeholder map address requirements and engagement.

  4. Question 26

    Which two statements about architecture governance in the TOGAF Standard are correct? (Choose two.)

    1. AIt establishes a framework of roles, processes and controls for managing architecture across the enterprise
    2. BIt is a single review held at the end of the migration program, after which it is closed
    3. CIt records governance decisions and their rationale in a governance log for later reference
    4. DIt replaces the Architecture Board with the project steering group, which takes over compliance
    Show answer and explanation
    Correct answer: A, C

    Architecture governance sets up a framework of roles, processes and controls, and decisions are recorded in a governance log for later reference. Treating governance as a single end-of-program review, or replacing the Architecture Board with a steering group, both contradict the ongoing governance role TOGAF describes.

Architecture content (ADM outputs) (4 questions)

  1. Question 27

    Which output is produced in Phase A, is approved by the sponsor, and gives a summarized view of the target architecture and its business value?

    1. AThe Architecture Vision, which gives a summarized view of the target and its business value
    2. BThe Architecture Definition Document, which records the detailed target architecture
    3. CThe Architecture Contract, which is agreed during implementation governance in Phase G
    4. DThe Architecture Roadmap, which sequences the work packages and transition architectures over time
    Show answer and explanation
    Correct answer: A

    The Architecture Vision is produced in Phase A and gives a high-level summary of the target architecture and its business value, which the sponsor approves. The roadmap, the definition document and the contract are all developed in later stages of the ADM.

  2. Question 28

    A lead architect needs the document that describes the target business, information systems and technology architectures in detail, which the team refines across Phases B, C and D. Which work product is this?

    1. AThe Architecture Vision, which is a summary produced in Phase A
    2. BThe Architecture Change Request, which records a proposed change after deployment
    3. CThe Architecture Definition Document, which holds the baseline and target architectures
    4. DThe Architecture Contract, which records the agreement signed for implementation
    Show answer and explanation
    Correct answer: C

    The Architecture Definition Document holds the baseline and target architectures across the business, information systems and technology domains, and it is developed in Phases B to D. The vision is a Phase A summary, the change request arises in Phase H, and the contract is an implementation agreement.

  3. Question 29

    An architect distinguishes between an Architecture Building Block and a Solution Building Block. Which statement is correct?

    1. AAn ABB names the specific vendor product, while an SBB describes only functional requirements
    2. BAn ABB specifies functionality and interfaces, while an SBB implements them with specific products
    3. CAn SBB is produced in Phase A, while an ABB is produced only in Phase H as a change request
    4. DBoth are identical in content, and the terms differ only by the phase that uses them
    Show answer and explanation
    Correct answer: B

    Architecture Building Blocks specify required functionality and interfaces without naming implementations, while Solution Building Blocks realize them with specific products or vendors. The other options reverse the roles of the two blocks or claim they are identical, which is incorrect.

  4. Question 30

    A team lead asks what the Statement of Architecture Work defines before an architecture project starts. Which answer is correct?

    1. AThe detailed technical design of every application, interface and database used across the enterprise
    2. BThe scope, approach and deliverables for the architecture project, agreed with the sponsor
    3. CThe vendor selection for each technology platform in the organization
    4. DThe list of stakeholders who will be excluded from the architecture process
    Show answer and explanation
    Correct answer: B

    The Statement of Architecture Work defines the scope, approach and deliverables of an architecture project, and it is agreed with the sponsor. The other options describe detailed design, vendor selection and stakeholder exclusion, none of which is what this document defines.