All CompTIA exams

CompTIA PK0-005: CompTIA Project+

What the PK0-005 exam covers and what it costs, with a free 30-question practice test and an explanation for every answer.

At a glance
Duration
90 minutes
Questions on the exam
Maximum of 90
Passing score
710 (scale 100-900)
Level
Associate
Topic areas
5
Free practice questions
30
Full question bank
100 questions

What the PK0-005 exam covers

The topic areas in our PK0-005 question bank, with each one's share of the 100 practice questions.

PK0-005 cost and format

Exam codePK0-005
CertificationCompTIA Project+
VendorCompTIA
LevelAssociate
StatusActive
LanguagesEnglish, Japanese, Thai
ReleasedNovember 8, 2022

Last checked October 22, 2026 against the official CompTIA exam page.

PK0-005 sample questions

The first 5 questions from the free practice test. Open a question to see the answer and why it is right.

All 30 free questions
  1. Question 1Project Planning

    A team must define the work required to deliver the project, breaking the scope into smaller manageable components. Which technique is used?

    1. AWork breakdown structure (WBS)
    2. BA stakeholder influence map
    3. CA regional holiday calendar
    4. DA monthly budget spreadsheet
    Show answer and explanation
    Correct answer: A

    A WBS decomposes the scope into deliverables and work packages, which supports estimating and scheduling. A budget spreadsheet, a stakeholder map and a holiday calendar do not decompose the scope.

  2. Question 2Project Monitoring and Control

    A project's cost performance index (CPI) is below 1. What does this indicate?

    1. AThe project is spending more than the value of the work completed
    2. BThe project is under budget on a cost-to-date basis and has accumulated savings
    3. CThe project has no actual spending recorded in the cost ledger for this period
    4. DThe project is ahead of schedule in terms of delivered scope and milestone dates
    Show answer and explanation
    Correct answer: A

    A CPI below 1 means the cost of work performed exceeds its earned value, which indicates overspending. A CPI above 1 indicates under-budget performance, and the other statements do not follow from CPI.

  3. Question 3Project Execution

    A project manager notices that two team members have overlapping responsibilities and are duplicating effort. Which action is most appropriate?

    1. AAsk both members to work faster and extend hours
    2. BClarify roles and responsibilities using a responsibility matrix
    3. CRemove one team member without discussion or a documented handover plan
    4. DIgnore the duplication until the project formally closes in the final review
    Show answer and explanation
    Correct answer: B

    A responsibility matrix clarifies roles and removes duplication in a structured way. Working faster, removing people without discussion and ignoring duplication do not resolve the root cause.

  4. Question 4Project Initiation

    A sponsor asks the project manager to define the high-level purpose and boundaries of a new initiative before detailed planning begins. Which document should be created?

    1. AA project charter that states the purpose, high-level scope, stakeholders and authority
    2. BA detailed Gantt chart with every task, duration, dependency and owner
    3. CA risk register with no context, no owners, no probability ratings and no assigned response plans
    4. DA procurement contract with a vendor, specifying payment schedules, penalty clauses and warranty terms
    Show answer and explanation
    Correct answer: A

    The project charter authorizes the project and records its purpose, high-level scope, stakeholders and authority. A detailed schedule comes later in planning, a risk register alone lacks context, and a contract is a procurement document.

  5. Question 5Project Closing

    A project is complete, and the customer has accepted the deliverables. Which activity should be done next to close the project formally?

    1. AStart a new project with the same team immediately without review
    2. BDelete all project records
    3. CObtain formal acceptance and archive the project documents
    4. DIgnore the lessons learned
    Show answer and explanation
    Correct answer: C

    Formal acceptance and archiving complete the project administratively and preserve records. Starting new work without review, deleting records and ignoring lessons learned are poor closing practices.

How to prepare for PK0-005

  1. Read the official CompTIA outline first (exam page), so you know exactly what is in scope.
  2. Give the most time to Project Planning and Project Monitoring and Control: together they make up 59% of the questions.
  3. Take the free 30-question practice test and note which topics you miss.
  4. Go back to the weak topics, then test again. A practice score shows where to study; it does not predict your exam result.

Full PK0-005 question bank

All 100 questions with answers and explanations, as a PDF, an online practice exam, or both.

Full question bank
Coming to the store soon

The full 100-question bank for PK0-005 is in final review. The free practice test is open now.

Start the free practice test

PK0-005 FAQ

Related exams

ExamVendorLevel
CAS-005: CompTIA SecurityXCompTIAExpert
CS0-004: CompTIA CySA+ (V4)CompTIAProfessional
CV0-004: CompTIA Cloud+CompTIAProfessional
CY0-001: CompTIA SecAI+CompTIAProfessional
DA0-002: CompTIA Data+CompTIAAssociate
FC0-U71: CompTIA Tech+CompTIAFoundational