Free PRINCE2 Project Management Foundation (Version 7) practice test: 30 questions with answers
30 original questions for PRINCE2 Project Management Foundation (Version 7), drawn from every topic area. Answer each one to see whether you got it right and why. No sign-up.
- Free questions
- 30
- Full bank
- 112 questions
- Real exam
- 60 questions, 60 min
- Passing score
- 60%
PRINCE2 Project Management Foundation (Version 7) exam guide: topics, cost and format
All 30 PRINCE2 Project Management Foundation (Version 7) questions with answers
The same questions as the test above, grouped by exam topic. Open any question to see the answer and explanation.
Project Management Principles (4 questions)
Question 1
A project has been running for several months. A new market analysis shows that the benefits it was set up to deliver are now unlikely to justify its remaining cost. Which PRINCE2 principle requires the Project Board to keep checking whether the project remains worthwhile?
- AManage by exception
- BDefined roles and responsibilities
- CFocus on products
- DContinued business justification
Show answer and explanationHide answer
Correct answer: DContinued business justification requires the business case to be checked throughout the project, so a project that no longer makes sense can be stopped. Manage by exception concerns escalation when tolerances are forecast to be exceeded, Focus on products concerns defined outputs and quality, and defined roles concerns who makes decisions.
Question 2
Which PRINCE2 principle means the project is planned, monitored and controlled in discrete parts, with a decision point at the end of each part?
- ALearn from experience
- BTailor to suit the project environment
- CManage by stages
- DFocus on products
Show answer and explanationHide answer
Correct answer: CManage by stages divides the project into stages, with a Project Board decision at each stage boundary. Learn from experience, Tailor to suit the project environment and Focus on products are other principles and do not define stage-based control.
Question 3
A Project Board gives its Project Manager a tolerance of plus or minus ten percent on cost and two weeks on time. The Project Manager runs the stage without reporting routine variances and only escalates when the forecast will breach those limits. Which principle is being applied?
- AManage by exception
- BManage by stages
- CLearn from experience
- DContinued business justification
Show answer and explanationHide answer
Correct answer: AManage by exception means the Board sets tolerances and intervenes only when a forecast breaches them, so routine variances stay with the Project Manager. Manage by stages is about dividing work into stages, not about thresholds, and the other two principles are not triggered by tolerance limits.
Question 4
A team starts building a new reporting service by listing the tasks they expect to do. Nobody has agreed what the finished service must include, how it will be tested, or who will accept it. Which principle has been overlooked?
- ALearn from experience
- BTailor to suit the project environment
- CManage by stages
- DFocus on products
Show answer and explanationHide answer
Correct answer: DFocus on products requires the expected outputs, their quality criteria and their acceptance to be defined before work starts, and that is missing here. Tailoring, managing by stages and learning from experience are real principles, but none of them is the one this scenario neglects.
Project Management Practices (4 questions)
Question 5
Which PRINCE2 practice covers identifying threats and opportunities, assessing them, and recording their owners and planned responses?
- AProgress
- BQuality
- COrganizing
- DRisk
Show answer and explanationHide answer
Correct answer: DThe risk practice deals with uncertainty: threats and opportunities are logged with owners and responses. Progress covers tracking performance against plans, Organizing covers roles and governance, and Quality covers standards and checks for products.
Question 6
After the scope was baselined, a stakeholder asks for an extra report that was not in the plan. The Project Manager records the request, assesses its effect on time and cost, and passes it to the change authority for a decision. Which practice does this activity belong to?
- AQuality
- BBusiness case
- CPlans
- DIssues
Show answer and explanationHide answer
Correct answer: DThe issues practice handles requests and issues that could alter the baseline, including impact assessment and decisions by a change authority. Business case, Plans and Quality are real areas, but they do not govern how a change request is recorded and decided.
Question 7
Which TWO activities are part of the quality practice? (Choose two.)
- ADefining quality criteria in product descriptions
- BRecording requests for changes in the issue register
- CReviewing delivered products against their acceptance criteria
- DTracking actual costs against the budget each month
Show answer and explanationHide answer
Correct answer: A, CThe quality practice covers defining quality expectations and checking products against them. Recording change requests belongs to the issues practice, and tracking costs against budget belongs to the progress and plans areas.
Question 8
Which practice focuses on the people, roles and governance structure of the project, including who is responsible for what?
- AProgress
- BOrganizing
- CBusiness case
- DRisk
Show answer and explanationHide answer
Correct answer: BThe organization practice defines the project's structure, roles and responsibilities. Progress covers tracking performance, Business case covers justification and benefits, and Risk covers uncertainty, so none of those describes the governance structure.
Project Management Processes (4 questions)
Question 9
Which process is used to decide whether a proposed project is worth pursuing before it is formally initiated, and to prepare the project brief?
- AStarting up a project
- BManaging product delivery
- CDirecting a project
- DClosing a project
Show answer and explanationHide answer
Correct answer: AStarting up a project is the pre-project process that checks whether the project is viable and prepares the project brief for initiation. Managing product delivery covers work package execution, Directing a project covers Board governance, and Closing a project ends the project.
Question 10
The Project Board has approved the current stage. As the stage nears its end, the Project Manager plans the next stage, updates the business case and risk register, and prepares the end stage report. Which process covers these activities?
- AManaging a stage boundary
- BControlling a stage
- CInitiating a project
- DClosing a project
Show answer and explanationHide answer
Correct answer: AManaging a stage boundary covers planning the next stage, updating the business case and risk register, and reporting the end of the stage. Controlling a stage covers day-to-day monitoring within a stage, while Initiating a project and Closing a project happen at the start and end of the whole project.
Question 11
The final products have been handed over to the customer's operations team, and the Project Board has received the end project report and a list of follow-on action recommendations. Which process is now being completed?
- AInitiating a project
- BDirecting a project
- CClosing a project
- DManaging product delivery
Show answer and explanationHide answer
Correct answer: CClosing a project covers product handover, the end project report, lessons and follow-on recommendations, and the Board's confirmation of closure. Directing a project is the Board's ongoing governance, Initiating a project happens at the start, and Managing product delivery covers creating individual products.
Question 12
Which THREE activities belong to the Managing product delivery process? (Choose three.)
- AAccepting a work package from the Project Manager
- BExecuting the work package to produce its products
- CDelivering completed products back to the Project Manager
- DApproving the project closure report on behalf of the Board
- EPreparing the business case for the next project
Show answer and explanationHide answer
Correct answer: A, B, CManaging product delivery covers accepting, executing and delivering work packages. Approving the closure report belongs to Closing a project, and preparing a business case for a future project sits outside this process.
Roles and Responsibilities (4 questions)
Question 13
A Project Board member is ultimately accountable for the project and owns its business case, and is responsible for making sure the project still delivers value to the organisation. Which role does this describe?
- ASenior User
- BProject Manager
- CExecutive
- DSenior Supplier
Show answer and explanationHide answer
Correct answer: CThe Executive is the single person accountable for the project and its business case on the Project Board. The Senior User represents the people who will use the product, the Senior Supplier represents those providing resources, and the Project Manager runs the project day to day.
Question 14
A Project Board member speaks for the people who will use the finished product. This role states the outcomes the users need, checks that the solution will meet them, and approves the final product from the user's point of view. Which role is this?
- ATeam Manager
- BSenior User
- CProject Support
- DProject Assurance
Show answer and explanationHide answer
Correct answer: BThe Senior User represents user interests and specifies outcomes and acceptance from the user's viewpoint. The Team Manager manages work packages, Project Support provides administrative services, and Project Assurance gives the Board an independent check on the project.
Question 15
Which TWO statements about the Project Manager role are correct? (Choose two.)
- AManages the project day to day within the tolerances set by the Project Board
- BApproves the project's business case on behalf of the Board
- CProduces stage plans and reports progress to the Project Board
- DAccepts personal liability for any cost overruns on the project
- EManages each individual team member's daily tasks in every work package
Show answer and explanationHide answer
Correct answer: A, CThe Project Manager runs the project day to day within the Board's tolerances and produces stage plans and progress reports. Business case ownership sits with the Executive and the Board, and daily management of work packages belongs to Team Managers.
Question 16
A Project Board member wants an independent view that the project's controls are being followed correctly, and reports this to the Board on its behalf. Which role provides this?
- AProject Support
- BProject Assurance
- CTeam Manager
- DSenior Supplier
Show answer and explanationHide answer
Correct answer: BProject Assurance gives the Board an independent check that controls are being followed, and it is held by Board members on the Board's behalf. Project Support provides administrative services, the Senior Supplier represents those providing resources, and the Team Manager runs work packages.
People Management (4 questions)
Question 17
A project team brings together people from three departments who have not worked together before. The Project Manager runs a kick-off where each member explains their role, skills and how they like to work. What is the main benefit of this session?
- ABuilding shared understanding and trust across the team
- BReplacing the need for a formal project plan
- CRemoving the need for regular progress meetings
- DCreating a list of approval limits for each manager
Show answer and explanationHide answer
Correct answer: AEarly sharing of roles, skills and working preferences builds mutual understanding and trust, which helps a team work well together. The other options are wrong because a kick-off does not replace the plan, does not remove the need for progress meetings, and does not set approval limits.
Question 18
A team member who has been reliable for months starts missing deadlines, and the quality of their work has dropped sharply. What should the Team Manager do first?
- ARemove the person from the work package immediately
- BTalk privately to find the cause and agree support
- CReport the person to the Project Board as an exception
- DReassign their tasks to others without discussing it with them
Show answer and explanationHide answer
Correct answer: BA private conversation finds out the cause of the drop in performance and lets the Team Manager agree practical support. Removing the person or reporting them to the Board skips this step, and reassigning work without discussion ignores the person's situation.
Question 19
What is the main purpose of a skills matrix in managing a project team?
- ATo rank team members by seniority for pay decisions
- BTo show each member's skills so tasks can be matched
- CTo record the stakeholder communication plan
- DTo list the risks owned by each team member
Show answer and explanationHide answer
Correct answer: BA skills matrix records the abilities of each person, which helps the Project Manager allocate work packages to suitable people. It is not a pay or seniority tool, a communication plan, or a risk register.
Question 20
Two specialists disagree about the technical approach for a stage. The Project Manager asks each to explain the concern behind their position, then agrees the criteria the options must meet and helps the pair choose. What does this approach illustrate?
- AEscalating the disagreement to the Executive without first discussing it with either specialist
- BResolving conflict through structured discussion based on agreed criteria
- CLetting the most senior specialist decide without discussion
- DPostponing the decision until after the project closes
Show answer and explanationHide answer
Correct answer: BAsking each person for the underlying concern and agreeing criteria before choosing an option is a structured way to resolve conflict within a team. The other options avoid the disagreement, skip discussion, or delay a decision that the stage needs.
Project Performance and Sustainability (4 questions)
Question 21
What is a tolerance in project performance management?
- AA fixed penalty applied when a supplier misses a milestone
- BThe total estimated cost of all identified project risks held in the register
- CThe minimum number of team members needed for a stage
- DThe permitted deviation from targets for time, cost, scope or quality
Show answer and explanationHide answer
Correct answer: DA tolerance is the allowed range of deviation that the Project Board sets for a plan's time, cost, scope, quality, risk and benefit. Penalties, team size and risk cost totals are not what a tolerance means.
Question 22
A Project Manager forecasts that the current stage will finish two weeks later than the time tolerance allows. The stage has not yet finished. What should the Project Manager do?
- AAbsorb the delay by quietly cutting testing time
- BAsk the team to work extra weekends without telling anyone
- CWait for the end stage report and include the delay there
- DRaise an exception report for the Project Board's decision
Show answer and explanationHide answer
Correct answer: DWhen a forecast breaches a tolerance, an exception report goes to the Project Board, which decides how to proceed. Hiding the deviation, absorbing it quietly or waiting until the stage ends leaves the Board uninformed.
Question 23
A project is replacing a production line. One option has a lower purchase price but uses much more energy over its working life. Which approach best reflects sustainable project decision-making?
- AChoosing the lowest purchase price and ignoring later running costs and energy use
- BLeaving environmental review until after the project has closed
- CComparing options on whole-life environmental impact and cost
- DDoing environmental checks only for projects above a fixed budget
Show answer and explanationHide answer
Correct answer: CSustainable decisions consider environmental and social effects over the product's whole life, not only the upfront cost. The other options ignore long-term energy use, postpone review until it can no longer change the decision, or limit checks by budget rather than by impact.
Question 24
A project is on time and within cost, but the Project Board is reviewing whether the outcomes it was meant to deliver are still expected. Which tolerance dimension is most directly under review?
- AQuality
- BScope
- CBenefit
- DRisk
Show answer and explanationHide answer
Correct answer: CBenefit tolerance concerns whether the outcomes the project was intended to achieve are still expected, which is what the Board is reviewing. Scope, quality and risk tolerances concern what is delivered, how well it performs and uncertainty, and the scenario does not describe any of those as the issue.
Digital and Data Management (3 questions)
Question 25
A project keeps its risk register, issue log and status figures in four separate spreadsheets. Different team members update different copies, and the Project Board receives conflicting figures. What is the most suitable improvement?
- AUse one controlled shared source of project data with version control
- BKeep separate copies so each team can work independently without waiting for others
- CStop recording issues and risks until the next stage starts
- DSend only the Project Manager's copy to the Board each month
Show answer and explanationHide answer
Correct answer: AOne controlled, shared source with version control keeps the Board's figures consistent and traceable. Separate copies, stopping the records or sending one person's copy only cause the inconsistency or hide information.
Question 26
Why is data quality important in project reporting?
- AIt is needed only for the final closure report
- BBoard decisions rely on accurate and timely information
- CIt removes the need to maintain a risk register
- DIt guarantees that the project will finish within its approved budget
Show answer and explanationHide answer
Correct answer: BThe Project Board makes decisions based on the information it receives, so accurate and timely data are essential. Data quality does not guarantee outcomes, does not remove the need for risk management, and is not only needed at closure.
Question 27
A project collects contact details and job titles from people who sign up to a pilot. Which action best shows responsible data management?
- ACollect all available customer details in case they turn out to be useful later on
- BStore the data in a shared folder that all staff can open
- CCollect only needed data, store it securely and follow data protection rules
- DKeep the data indefinitely so it can be reused on future projects
Show answer and explanationHide answer
Correct answer: CLimiting collection to what is needed, securing it and complying with data protection rules is responsible data management. Collecting extra data, sharing it widely or keeping it indefinitely each create avoidable risk.
Communication and Tailoring (3 questions)
Question 28
A five-person internal project must follow the organisation's PRINCE2 approach. Its team finds that the full set of documents and reviews delays the work. What should the Project Manager do?
- AAdapt the documents and reviews to the project's size, risk and environment
- BDrop the principles and run the project with no governance or controls at all
- CAsk the Project Board to exempt the project from all reporting
- DKeep every document and review because the method requires it
Show answer and explanationHide answer
Correct answer: ATailoring means adapting how the framework is applied to the project's size, risk and environment while keeping its principles. Dropping the principles or governance, or demanding full exemption from reporting, removes controls rather than tailoring them.
Question 29
What is the main purpose of a communication plan in a project?
- ATo list every risk that could delay the flow of information between the teams involved
- BTo define the information shared, the audience, the frequency and the channels
- CTo set the pay rates for the communications team and its managers
- DTo replace the need for stakeholder engagement across the project
Show answer and explanationHide answer
Correct answer: BA communication plan sets out the information, audiences, frequency and channels so that stakeholders receive what they need. It is not a risk list, a pay tool, or a substitute for engaging stakeholders.
Question 30
Which TWO actions show appropriate tailoring of PRINCE2 to a project? (Choose two.)
- AScaling the number and depth of reports to the project's size and complexity
- BRemoving the Project Board's authority to approve stage plans
- CAdjusting the level of documentation to match the project's risk profile
- DDropping the requirement to record issues because the team is small
- ESkipping stage boundaries whenever a stage seems to run smoothly
Show answer and explanationHide answer
Correct answer: A, CTailoring adapts the amount of documentation and reporting to the project's size, complexity and risk. It must not remove governance such as Board approval, issue recording or stage boundaries.