PRINCE2 Project Management Foundation (Version 7)

What the PRINCE2 Project Management Foundation (Version 7) exam covers and what it costs, with a free 30-question practice test and an explanation for every answer.

At a glance
Duration
60 minutes
Questions on the exam
60
Passing score
60%
Level
Foundational
Topic areas
8
Free practice questions
30
Full question bank
112 questions

What the PRINCE2 Project Management Foundation (Version 7) exam covers

The topic areas in our PRINCE2 Project Management Foundation (Version 7) question bank, with each one's share of the 112 practice questions.

PRINCE2 Project Management Foundation (Version 7) cost and format

CertificationPRINCE2 Project Management Foundation (Version 7)
VendorPeopleCert
LevelFoundational
StatusActive
Languages14 languages incl. English, Chinese, Czech, Danish, Dutch, French, German
DeliveryClosed book multiple choice

Last checked November 10, 2026 against the official PeopleCert exam page.

PRINCE2 Project Management Foundation (Version 7) sample questions

The first 5 questions from the free practice test. Open a question to see the answer and why it is right.

All 30 free questions
  1. Question 1Project Management Principles

    A project has been running for several months. A new market analysis shows that the benefits it was set up to deliver are now unlikely to justify its remaining cost. Which PRINCE2 principle requires the Project Board to keep checking whether the project remains worthwhile?

    1. AManage by exception
    2. BDefined roles and responsibilities
    3. CFocus on products
    4. DContinued business justification
    Show answer and explanation
    Correct answer: D

    Continued business justification requires the business case to be checked throughout the project, so a project that no longer makes sense can be stopped. Manage by exception concerns escalation when tolerances are forecast to be exceeded, Focus on products concerns defined outputs and quality, and defined roles concerns who makes decisions.

  2. Question 2Project Management Practices

    Which PRINCE2 practice covers identifying threats and opportunities, assessing them, and recording their owners and planned responses?

    1. AProgress
    2. BQuality
    3. COrganizing
    4. DRisk
    Show answer and explanation
    Correct answer: D

    The risk practice deals with uncertainty: threats and opportunities are logged with owners and responses. Progress covers tracking performance against plans, Organizing covers roles and governance, and Quality covers standards and checks for products.

  3. Question 3Project Management Processes

    Which process is used to decide whether a proposed project is worth pursuing before it is formally initiated, and to prepare the project brief?

    1. AStarting up a project
    2. BManaging product delivery
    3. CDirecting a project
    4. DClosing a project
    Show answer and explanation
    Correct answer: A

    Starting up a project is the pre-project process that checks whether the project is viable and prepares the project brief for initiation. Managing product delivery covers work package execution, Directing a project covers Board governance, and Closing a project ends the project.

  4. Question 4Roles and Responsibilities

    A Project Board member is ultimately accountable for the project and owns its business case, and is responsible for making sure the project still delivers value to the organisation. Which role does this describe?

    1. ASenior User
    2. BProject Manager
    3. CExecutive
    4. DSenior Supplier
    Show answer and explanation
    Correct answer: C

    The Executive is the single person accountable for the project and its business case on the Project Board. The Senior User represents the people who will use the product, the Senior Supplier represents those providing resources, and the Project Manager runs the project day to day.

  5. Question 5People Management

    A project team brings together people from three departments who have not worked together before. The Project Manager runs a kick-off where each member explains their role, skills and how they like to work. What is the main benefit of this session?

    1. ABuilding shared understanding and trust across the team
    2. BReplacing the need for a formal project plan
    3. CRemoving the need for regular progress meetings
    4. DCreating a list of approval limits for each manager
    Show answer and explanation
    Correct answer: A

    Early sharing of roles, skills and working preferences builds mutual understanding and trust, which helps a team work well together. The other options are wrong because a kick-off does not replace the plan, does not remove the need for progress meetings, and does not set approval limits.

How to prepare for PRINCE2 Project Management Foundation (Version 7)

  1. Read the official PeopleCert outline first (exam page), so you know exactly what is in scope.
  2. Give the most time to Project Management Principles and Project Management Practices: together they make up 26% of the questions.
  3. Take the free 30-question practice test and note which topics you miss.
  4. Go back to the weak topics, then test again. A practice score shows where to study; it does not predict your exam result.

Full PRINCE2 Project Management Foundation (Version 7) question bank

All 112 questions with answers and explanations, as a PDF, an online practice exam, or both.

Full question bank
Coming to the store soon

The full 112-question bank for PRINCE2 Project Management Foundation (Version 7) is in final review. The free practice test is open now.

Start the free practice test

PRINCE2 Project Management Foundation (Version 7) FAQ