Free PRINCE2 Project Management Practitioner (Version 7) practice test: 30 questions with answers

30 original questions for PRINCE2 Project Management Practitioner (Version 7), drawn from every topic area. Answer each one to see whether you got it right and why. No sign-up.

Free questions
30
Full bank
112 questions
Real exam
56 questions, 150 min
Passing score
60%

PRINCE2 Project Management Practitioner (Version 7) exam guide: topics, cost and format

All 30 PRINCE2 Project Management Practitioner (Version 7) questions with answers

The same questions as the test above, grouped by exam topic. Open any question to see the answer and explanation.

PRINCE2 Principles (4 questions)

  1. Question 1

    A project's benefits are no longer achievable at a reasonable cost after a shift in the market. The Project Board wants a principle that makes it check, at each point, whether the project is still worth doing. Which principle applies?

    1. AContinued business justification, so the business case is checked throughout the project
    2. BFocus on products, so the outputs and their quality criteria are defined before work on them begins
    3. CManage by exception, so the Project Board only reviews the project when a tolerance is forecast to be breached
    4. DTailor to suit the project environment, so the method is adjusted to the size, risk and complexity of the work
    Show answer and explanation
    Correct answer: A

    Continued business justification requires the business case to be reviewed throughout the project, so the project continues only while it remains viable and desirable. Manage by exception concerns tolerances, focus on products concerns outputs and quality, and tailoring concerns adapting the method, so none of them directly tests ongoing viability.

  2. Question 2

    Which PRINCE2 principle is concerned with capturing lessons from earlier stages and projects and using them to improve future work?

    1. ALearn from experience, so lessons are captured in a lessons log and used to improve future work
    2. BManage by stages, so the project is controlled through a single plan for the whole life of the work
    3. CDefined roles and responsibilities, so that each person in the project organisation knows what they must do
    4. DManage by exception, so the Project Board intervenes only when a tolerance is forecast to be breached
    Show answer and explanation
    Correct answer: A

    The learn from experience principle asks teams to record lessons in a log and review them so they can be applied to later stages and projects. The other principles address stage control, organisational clarity and tolerance-based escalation, not the reuse of lessons.

  3. Question 3

    A software team starts building a reporting tool without agreed criteria for what each output must do. Testing reveals repeated rework. Which principle would have prevented this?

    1. AFocus on products, so each output is defined with quality criteria before work to produce it starts
    2. BContinued business justification, so the business case is revisited whenever the scope of the work changes
    3. CManage by exception, so the Project Board is only informed when tolerances are at risk of being exceeded
    4. DTailor to suit the project environment, so the level of documentation matches the size of the work
    Show answer and explanation
    Correct answer: A

    Focus on products requires products and their quality criteria to be defined before work starts, which prevents rework caused by unclear requirements. Tailoring, business justification and management by exception are real principles but do not address defining outputs before building them.

  4. Question 4

    A Project Manager leading a small, low-risk internal project removes several management products that the standard method describes, to avoid unnecessary effort. Which principle does this reflect?

    1. AManage by stages, dividing the work into stage plans with defined stage boundaries as control points
    2. BDefined roles and responsibilities, with each person's authority, reporting lines and duties recorded in role descriptions
    3. CTailor to suit the project environment, adjusting the method to the size and risk of the work
    4. DLearn from experience, capturing lessons in a lessons log so that later projects can benefit from earlier work
    Show answer and explanation
    Correct answer: C

    Tailoring means adjusting the method, including its products and processes, to suit the project's context, so a small low-risk project can use less documentation. The other principles describe stage control, role clarity and lessons, none of which justifies removing products.

PRINCE2 Practices (4 questions)

  1. Question 5

    A team identifies a risk that a supplier's late delivery could push a key product past its agreed date. The Project Manager logs it with its probability, impact and a proposed response. Which PRINCE2 practice does this activity belong to?

    1. ARisk practice, which identifies, assesses and responds to uncertainty that could affect objectives
    2. BQuality practice, which defines the standards that products must meet and how those standards will be checked
    3. CProgress practice, which tracks performance against the plan and the agreed tolerances over time
    4. DIssues practice, which handles problems, requests for change and off-specifications to the agreed baselines of the project
    Show answer and explanation
    Correct answer: A

    The risk practice covers identifying, assessing and planning responses to uncertainty, including logging risks in the risk register. Quality, progress and issues are separate practices that address standards, performance tracking and change control respectively.

  2. Question 6

    What is the main purpose of a product description in a PRINCE2 project?

    1. AIt records the cost and time tolerances approved by the Project Board for the stage in which the product is delivered
    2. BIt lists the tasks, effort and dependencies a team needs to complete a work package on time and to budget
    3. CIt sets out a product's purpose, composition, format and quality criteria
    4. DIt summarises the risks that could stop a product from being delivered and the responses agreed for each one
    Show answer and explanation
    Correct answer: C

    A product description defines what a product is for, what it contains, its format and the criteria it must meet, which forms the basis for quality checks. The other options describe tolerance records, work package content and the risk register respectively.

  3. Question 7

    A Project Manager needs to show the Project Board how the project's products will be delivered, when, what they will cost and the tolerances that apply across the whole project. Which document should be used?

    1. AA daily log that records the actions, observations and informal decisions the Project Manager makes each day
    2. BA project plan that shows the products, timescales, costs and tolerances for the whole project
    3. CA lessons report that summarises what worked well and what did not in the earlier stages of the project
    4. DA highlight report that gives the Project Board a short summary of progress in the latest reporting period
    Show answer and explanation
    Correct answer: B

    The project plan is the high-level plan for the whole project, covering products, timescales, costs and tolerances. The daily log, lessons report and highlight report each serve other purposes and do not give the full project-level view.

  4. Question 8

    A Project Manager wants one record that holds a summary of all the quality management activities planned and carried out in the project, with their dates and outcomes. Which management product is used?

    1. AQuality register, which summarises planned and completed quality management activities
    2. BRisk register, which records each risk with its owner, probability, impact and response
    3. CDaily log, which holds the Project Manager's informal notes and observations
    4. DHighlight report, which gives the Project Board a short summary of progress for a period
    Show answer and explanation
    Correct answer: A

    The quality register holds a summary of the quality management activities planned and performed, together with their dates and results. The risk register, daily log and highlight report hold risk, informal and progress information respectively.

PRINCE2 Processes (4 questions)

  1. Question 9

    The Project Board must decide whether to formally approve the project to move into delivery after initiation has been completed. Which process contains this decision?

    1. AStarting up a Project, in which the project brief and outline business case are prepared
    2. BControlling a Stage, in which the Project Manager assesses progress against each work package
    3. CInitiating a Project, in which the Project Initiation Documentation is created and approved
    4. DDirecting a Project, in which the Project Board authorises the project and each stage
    Show answer and explanation
    Correct answer: D

    Directing a Project covers the Project Board's decisions, including authorising the project and each stage. The other processes prepare the project, create the initiation documents or control day-to-day work within a stage.

  2. Question 10

    What is the main purpose of the Managing a Stage Boundary process?

    1. ATo capture and review the issues and risks raised during the stage in the daily log before the stage ends
    2. BTo authorise each work package the Project Manager issues to a Team Manager for product delivery and review
    3. CTo confirm that all products have been handed over and that the Project Board can recommend project closure
    4. DTo prepare the next stage plan and update the business case, risks and plans before the next stage begins
    Show answer and explanation
    Correct answer: D

    Managing a Stage Boundary is where the Project Manager plans the next stage, updates the business case, risks and plans, and reports the end of the stage to the Project Board. Authorising work packages belongs to Controlling a Stage and handover to Closing a Project.

  3. Question 11

    A project has delivered all its products and the customer has accepted them. The Project Manager now needs to hand the products over, release resources and recommend the project for closure. Which process covers this?

    1. AManaging Product Delivery, in which Team Managers accept, execute and deliver the work packages they are given
    2. BControlling a Stage, in which the Project Manager assesses progress and takes corrective action where needed
    3. CDirecting a Project, in which the Project Board gives ad hoc direction and makes the key decisions
    4. DClosing a Project, in which products are handed over and the project is shut down in an orderly way
    Show answer and explanation
    Correct answer: D

    Closing a Project covers handover of products, release of resources and the recommendation to close, which fits the scenario. Managing Product Delivery and Controlling a Stage cover work during a stage, and Directing a Project covers Board decisions rather than closing activities.

  4. Question 12

    Before a project's initiation begins, which process appoints the key people and plans the initiation stage?

    1. AStarting up a Project, which appoints the Executive and Project Manager and plans initiation
    2. BClosing a Project, in which the products are handed over and resources are released to the business
    3. CManaging a Stage Boundary, in which the next stage plan and the updated business case are prepared
    4. DControlling a Stage, which authorises work packages and reviews progress against the stage plan regularly
    Show answer and explanation
    Correct answer: A

    Starting up a Project is the preliminary process in which the Executive and Project Manager are appointed, the outline business case and project brief are prepared, and the initiation stage is planned. The other processes apply to later parts of the project's life cycle.

Key Roles and Responsibilities (4 questions)

  1. Question 13

    The Project Board wants routine change requests under a set limit to be decided without waiting for a full Board meeting. Which role should be given this delegated authority?

    1. AChange Authority, which decides on requests for change within a limit delegated by the Project Board
    2. BProject Assurance, which provides independent checks on the project's business, user and supplier interests
    3. CProject Support, which provides administrative services such as document control and configuration management
    4. DTeam Manager, which manages the people who produce the products allocated to them in work packages
    Show answer and explanation
    Correct answer: A

    The Change Authority can be given delegated authority by the Project Board to approve or reject change requests within agreed limits. Project Assurance checks interests on the Board's behalf, Project Support provides administrative services, and Team Managers deliver products, so none of them is the right delegate for change decisions.

  2. Question 14

    Which PRINCE2 role is ultimately accountable for the project and for its business justification?

    1. AProject Manager, who is responsible for day-to-day management of the project within the agreed tolerances
    2. BSenior Supplier, who provides the resources and expertise needed to build and deliver the project's products
    3. CExecutive, who is ultimately accountable for the project and for its business justification
    4. DSenior User, who makes sure the outputs meet user needs and deliver the expected benefits
    Show answer and explanation
    Correct answer: C

    The Executive is the Project Board member who is ultimately accountable for the project, including keeping the business justification valid. The Project Manager runs day-to-day management, the Senior Supplier provides supplier resources and the Senior User represents the users.

  3. Question 15

    Which TWO of the following are responsibilities of Project Assurance? (Choose two.)

    1. AChecking that the outputs will continue to meet the needs of the users throughout the project
    2. BWriting the detailed work packages and issuing them to Team Managers each week
    3. CChecking that the supplier side has the resources and skills needed to deliver the products
    4. DApproving the stage tolerances and the overall budget on behalf of the Project Board
    5. EMaintaining the lessons log and the configuration library for the project's products
    Show answer and explanation
    Correct answer: A, C

    Project Assurance gives independent checks for the Project Board, covering business, user and supplier assurance. Writing work packages is a Project Manager task, approving tolerances and budgets belongs to the Project Board, and maintaining logs and configuration libraries is a Project Support task.

  4. Question 16

    A project depends heavily on an external supplier. Which responsibility belongs to the Senior Supplier on the Project Board?

    1. ARepresenting the interests of those who design and build the products, and committing supplier resources
    2. BSetting the user acceptance criteria and confirming that the outputs will deliver the expected benefits
    3. CManaging the project's daily work and allocating each work package to the Team Managers
    4. DMaintaining the lessons log and the configuration library for every stage of the project
    Show answer and explanation
    Correct answer: A

    The Senior Supplier represents the interests of those who design and build the products and commits supplier resources to the project. The user acceptance role belongs to the Senior User, daily management to the Project Manager, and administration to Project Support.

People Management and Collaboration (4 questions)

  1. Question 17

    Two team members strongly disagree about how a product should be designed, and the disagreement is slowing progress. What should the Project Manager do first?

    1. AAsk the Project Board to decide the design now so that the work can continue without any further delay
    2. BBring both people together to explore their views and agree the criteria the product must meet
    3. CGive the design task to whichever team member has the most seniority so the discussion can end quickly
    4. DLeave the disagreement alone until testing, when the design can be checked objectively against results
    Show answer and explanation
    Correct answer: B

    Bringing the people together to explore views and agree the product's criteria is the collaborative first step, and keeps the decision grounded in agreed requirements. Escalating immediately, imposing a decision by seniority or delaying the issue until testing each skip the attempt to resolve it within the team.

  2. Question 18

    What is the main benefit of defining roles and responsibilities clearly for each member of a project team?

    1. AIt means the Project Board no longer needs to review the business case at each stage boundary
    2. BIt removes the need for the Project Manager to monitor progress, because people report directly to their own line managers
    3. CIt allows team members to choose which products they would like to work on as the project progresses
    4. DIt reduces duplicated effort and gaps in ownership because each person knows what they are accountable for
    Show answer and explanation
    Correct answer: D

    Clear roles and responsibilities reduce duplicated effort and gaps in ownership, which is the point of the defined roles principle. The other options wrongly suggest that monitoring, product choice or Board review can be dropped.

  3. Question 19

    A Team Manager notices that a usually active team member has stopped contributing in meetings. Which action best supports motivation and collaboration?

    1. AReassign the team member to a less visible task so the team can concentrate on the work that matters most
    2. BHold a one-to-one conversation to understand the cause and agree support or changed responsibilities
    3. CRemind the whole team in the next meeting that every member is expected to speak up in every session
    4. DRecord the lack of contribution in the lessons log so future projects avoid the same team members
    Show answer and explanation
    Correct answer: B

    A one-to-one conversation lets the manager find the cause of the change and agree support, which is the collaborative and motivating response. The other options sideline the person, misuse the lessons log or address the whole team when the problem is with one individual.

  4. Question 20

    Which THREE actions help a Project Manager build an effective, collaborative project team? (Choose three.)

    1. AAgreeing team goals and how the team's success will be recognised
    2. BHolding regular team meetings where people can raise concerns openly
    3. CKeeping individual responsibilities hidden until the final product review
    4. DSetting clear roles and responsibilities for each person in the team
    5. ELimiting all communication to written reports sent through the Project Support office
    Show answer and explanation
    Correct answer: A, B, D

    Shared goals, open meetings and clear roles all help a team collaborate and stay accountable. Hiding responsibilities and restricting all communication to written reports both weaken collaboration and clarity.

Sustainability and ESG (4 questions)

  1. Question 21

    A project will replace office IT equipment. The Project Manager wants environmental impacts considered from the start, not left until the end. Which action reflects this?

    1. AExclude environmental impacts from the business case because they do not affect the project's budget
    2. BWait until the products are delivered before considering how they will be disposed of at end of life
    3. CInclude energy use and disposal in the business case and in the quality criteria for the products
    4. DRemove all sustainability questions from the project so that scope stays limited and the schedule stays firm
    Show answer and explanation
    Correct answer: C

    Recording energy use and disposal in the business case and in the product quality criteria builds sustainability into decisions from the start. The other options postpone or exclude environmental impacts, which conflicts with considering them throughout the project.

  2. Question 22

    Which item is most appropriate to record in the risk register as a sustainability-related risk?

    1. AThe project may exceed its contingency budget if a planned room is booked late for an internal workshop
    2. BTeam members may need to update the daily log after each working session so that records stay current
    3. CSuppliers' labour practices may prove unacceptable, damaging the sponsoring organisation's reputation
    4. DThe Project Board membership may change before the next stage boundary, affecting who approves decisions
    Show answer and explanation
    Correct answer: C

    A risk about supplier labour practices is a social and governance risk that could cause reputational harm, so it belongs in the risk register. The other items concern scheduling, logging and governance administration rather than sustainability.

  3. Question 23

    Which TWO of the following show how sustainability can be built into a project's management? (Choose two.)

    1. AIncluding environmental and social criteria in product descriptions
    2. BTreating sustainability as a separate report written only after the project has closed
    3. CRecording the sustainability impact of key decisions in the business case and reviewing it at stage boundaries
    4. DChoosing the cheapest supplier regardless of its environmental record, so the budget is protected
    5. ELeaving sustainability to the Project Board to decide after the products have been handed over
    Show answer and explanation
    Correct answer: A, C

    Environmental and social criteria in product descriptions, and recording sustainability impacts in the business case reviewed at stage boundaries, both build sustainability into ongoing decisions. The other options postpone sustainability or ignore it in favour of cost alone.

  4. Question 24

    A project plans four workshops with suppliers in different countries. The Project Manager wants to reduce environmental impact without slowing decisions. Which action is most appropriate?

    1. ACancel the workshops and make all decisions by email, which removes the need for travel and meetings
    2. BKeep all workshops in person, because the environmental effects of travel are outside the project's scope
    3. CHold workshops online where they work well, and record the travel impact in the business case
    4. DHold the workshops in person but book the cheapest flights, so the project's budget is best protected
    Show answer and explanation
    Correct answer: C

    Online workshops where they work well reduce travel impact, and recording that impact in the business case keeps the trade-off visible to decision makers. The other options ignore environmental impact, drop the decision forums or protect budget at the expense of sustainability.

Digital and Data Management (3 questions)

  1. Question 25

    A project team keeps its risk, issue and change logs in several separate spreadsheets, and the versions regularly fall out of step. Which approach best solves this?

    1. APrint each log at the end of every week and file the printouts in the project office for reference
    2. BLet each team member keep a personal copy of the logs so that no one waits for others to update them
    3. CUse one controlled set of logs in a shared digital tool with a single owner and a version history
    4. DStore the logs on a personal laptop so they can be updated quickly and kept away from network access
    Show answer and explanation
    Correct answer: C

    One controlled set of logs in a shared digital tool, with a single owner and a version history, keeps the information consistent. Printing or personal copies create more versions, and storing logs on a personal device adds risk without fixing the consistency problem.

  2. Question 26

    Why does a project benefit from a single source of truth for its data?

    1. AIt allows the Project Board to skip reviewing reports, since the data is considered to speak for itself
    2. BIt removes the need to define quality criteria for the products the project will deliver
    3. CIt ensures all data is stored in the cheapest available system, regardless of its security
    4. DIt means different people make decisions from the same current and consistent information
    Show answer and explanation
    Correct answer: D

    A single source of truth keeps decisions consistent because everyone works from the same current information. Skipping report reviews, dropping quality criteria and choosing systems only on cost are each wrong for different reasons.

  3. Question 27

    A project collects personal data from users through a survey. The Project Manager needs to handle the data responsibly. Which action is most appropriate?

    1. AKeep all responses in a shared folder that the whole organisation can open, in case someone needs them later
    2. BCollect only the data needed, limit access to those who need it and set a deletion date
    3. CRetain all responses indefinitely so they can be analysed again if the project scope changes later
    4. DCopy the responses to the project's public website so that stakeholders can see the results directly
    Show answer and explanation
    Correct answer: B

    Collecting only the data needed, restricting access and setting a deletion date are standard practice for handling personal data responsibly. The other options expose the data publicly or internally without need, or keep it longer than necessary.

Effective Communication Methods and Tailoring (3 questions)

  1. Question 28

    A design change affects both technical leads and non-technical sponsors. The Project Manager must communicate it to both groups. Which approach best tailors the communication?

    1. ASend the same detailed technical document to every stakeholder so that everyone has identical information
    2. BA short impact summary for sponsors, with the technical detail provided to the technical leads
    3. CShare the change verbally at the next team meeting and rely on people to ask questions if they need to
    4. DHold back the change until the design is complete so that stakeholders receive one final version
    Show answer and explanation
    Correct answer: B

    Tailoring means giving each audience the level of detail and format it needs, so sponsors receive an impact summary while leads get the technical detail. Identical documents, verbal-only sharing or waiting until the end each fail to meet the needs of one group or the other.

  2. Question 29

    Which statement best describes tailoring of the communication approach in a PRINCE2 project?

    1. AUsing one standard report template for every project so that Project Boards can compare progress across the portfolio
    2. BAdapting communication frequency, format and content to suit the project and its stakeholders
    3. CRemoving communication with stakeholders who are not on the Project Board to keep the project focused
    4. DKeeping the communication approach fixed from initiation to closure so that changes are easier to track
    Show answer and explanation
    Correct answer: B

    Tailoring the communication approach means adapting how often the project communicates, in what format and with what content, to suit its size, complexity and stakeholders. The other options describe fixed templates, excluding stakeholders or never changing the approach, all of which contradict tailoring.

  3. Question 30

    A project's highlight report is consistently ignored by the Project Board because it is long and full of detail. What should the Project Manager change?

    1. AKeep the same report but send it more often so that Board members see progress more regularly
    2. BAdd more technical detail to the report so that Board members can fully understand the underlying issues
    3. CStop reporting to the Project Board until a serious exception occurs, so that their time is not wasted
    4. DShorten the report to the key progress, risks and issues, in a format agreed with the Project Board
    Show answer and explanation
    Correct answer: D

    Highlight reports should give the Project Board concise progress, risk and issue information in a format the Board has agreed. Adding detail, sending the same report more often or reporting only on exceptions each fail to meet the Board's need for a concise, agreed summary.